OEE Calculator

Multiply availability, performance and quality to see how well a machine used its planned time.

Your numbers

Stops, changeovers and breakdowns inside the planned time.

The fastest steady time per unit, not an average.

Good and bad units together.

Result

Overall equipment effectiveness

76.9%

Availability 90.2% x performance 90.1% x quality 94.6%.

Availability
90.2%
Performance
90.1%
Quality
94.6%
Run time
433 min
Time needed at the ideal rate
390 min
Good time (good units at the ideal rate)
369 min
Rejected units
42
How this was calculated
  1. Run time = planned - downtime = 480 - 47 = 433 min. Availability = run / planned = 0.9021.
  2. Performance = (ideal cycle x total units) / run time = (30 s x 780 / 60) / 433 = 0.9007.
  3. Quality = good / total = 738 / 780 = 0.9462.
  4. OEE = 0.9021 x 0.9007 x 0.9462 = 0.7687. It also equals good units x ideal cycle / planned time.
  • OEE depends on what you count as planned time, downtime and the ideal cycle time, so compare it only with figures that use the same definitions. No target or benchmark is built in. Use the three parts to see where time is being lost.

Calculated using SumPanda.com · https://sumpanda.com/oee-calculator/

Results are estimates for general information. Verify important figures before relying on them.

Next step

How to use the oee calculator

  1. Enter the planned production time in minutes and the downtime inside it.
  2. Enter the ideal cycle time in seconds per unit, the fastest steady time the line can make one.
  3. Enter the total units made and the good units.
  4. Read the headline OEE and the three parts, availability, performance and quality, to see where the time was lost. Copy, Print or export the CSV.

Formula

availability = (planned time - downtime) / planned time

performance = (ideal cycle time x total units) / run time

quality = good units / total units

OEE = availability x performance x quality

Times are converted to minutes. OEE also equals good units times the ideal cycle time, divided by the planned time. If performance would be above 100%, the page asks you to check the cycle time and counts.

One 8 hour shift

Planned time is 480 minutes with 47 minutes of downtime, so the machine ran 433 minutes and availability is 433 / 480 = 90.2%. At an ideal 30 seconds per unit, 780 units should take 390 minutes, so performance is 390 / 433 = 90.1%.

Of 780 units, 738 were good, so quality is 94.6%. OEE is 0.9021 x 0.9007 x 0.9462 = 76.9%, which matches 738 x 30 seconds / 60 / 480 minutes = 0.76875.

Reading the three parts

Availability shows time lost to stops, such as breakdowns and changeovers. Performance shows time lost to running slower than the ideal rate, including small stops. Quality shows output lost to rejects and rework. Because they multiply, a modest loss in each part adds up to a larger loss overall.

The part with the lowest percentage is usually the best place to start looking, but the cost of fixing each one is different, so use the numbers as a guide and not a verdict.

Definitions matter

OEE depends on what you count as planned time, what counts as downtime and how the ideal cycle time was chosen. A generous ideal makes performance look poor and a cautious one makes it look good. Compare OEE only against numbers that use the same definitions, and write them down.

No target is built in, because good values differ by process and industry. For related inventory and operations tools, see the economic order quantity calculator, the reorder point calculator and the inventory turnover calculator.

Assumptions and limits

  • Downtime must be less than planned time, and good units cannot exceed total units.
  • At least one unit must be made so that performance and quality can be measured.
  • Performance above 100% is refused, because it usually means the ideal cycle time or a count is wrong.
  • Nothing is stored or uploaded, and no benchmark is built in.

Formulas reviewed October 10, 2026. See the calculation methodology for how SumPanda rounds, tests and sources its formulas.

Frequently asked questions

How do you calculate OEE?

Multiply availability, performance and quality. Availability is run time over planned time, performance is ideal cycle time times total units over run time, and quality is good units over total units.

What is a good OEE?

This page does not set a target. Good values depend on the process and on how planned time and the ideal cycle time are defined, so compare with your own past figures using the same definitions.

What is the ideal cycle time?

It is the fastest steady time to make one unit under good conditions, such as the rated speed of the machine. Using an average instead of the fastest rate hides performance losses.

Why did the page refuse my numbers?

Performance came out above 100%, meaning the units you made would have taken less time than the machine ran at the ideal rate. Check the cycle time, the unit count and the run time.