Critical Chain Buffer Calculator

List tasks with a safe and an aggressive estimate to see the buffer and the planned duration.

Your numbers

Task, safe estimate and aggressive estimate in the same unit (such as days), separated by commas. The safe estimate must be at least the aggressive one.

More options

Result

Project buffer

11.00 days

Planned duration 44.00 days, against 55.00 days with every safe estimate added up.

Sum of safe estimates
55.00 days
Sum of aggressive estimates
33.00 days
Safety removed from the tasks
22.00 days
Buffer by cut and paste (half)
11.00 days
Buffer by root of summed squares
10.86 days
Planned duration with the buffer
44.00 days
Time saved against the safe total
11.00 days

Tasks

TaskSafeAggressiveSafety removed
Design1064
Build20128
Integrate853
Test1275
Release532
Total553322
How this was calculated
  1. For each task, the safety removed is the safe estimate minus the aggressive estimate.
  2. Cut and paste: the buffer is half of all the safety removed. Root of summed squares: the buffer is the square root of the sum of each task’s safety removed, squared.
  3. The planned duration is the sum of the aggressive estimates plus the buffer, which sits at the end of the chain.
  4. The root method gives a smaller buffer than half when many tasks share the safety, because delays rarely all happen at once.
  • Both methods are rules of thumb from critical chain scheduling, and the root method assumes task delays are independent. They size the buffer, but they do not tell you how fast it is used up. Track consumption against progress while the project runs.

Calculated using SumPanda.com · https://sumpanda.com/critical-chain-buffer-calculator/

Results are estimates for general information. Verify important figures before relying on them.

Next step

How to use the critical chain buffer calculator

  1. List the tasks on the chain with a safe estimate and an aggressive estimate in the same unit, separated by commas.
  2. Choose the buffer method: cut and paste, which takes half of the safety removed, or the root of summed squares.
  3. Change the unit label in the advanced section if you like. The default is days.
  4. Read the buffer, the planned duration, the time saved against the safe total and both methods side by side.

Formula

safety removed = safe estimate - aggressive estimate, for each task

cut and paste buffer = 50% of the total safety removed

root of summed squares buffer = sqrt(sum of (safe - aggressive)^2)

planned duration = sum of aggressive estimates + buffer

The aggressive estimate is the time a task takes if things go well, and the safe estimate allows for trouble. Critical chain planning removes the padding from tasks and puts a shared buffer at the end.

Five tasks

The sample tasks have safe estimates of 10, 20, 8, 12 and 5 days, which add up to 55, and aggressive estimates of 6, 12, 5, 7 and 3 days, which add up to 33. The safety removed is 22 days.

By cut and paste the buffer is 11 days, so the planned duration is 33 + 11 = 44 days, 11 days less than the safe total. By the root method the squares are 16, 64, 9, 25 and 4, which add up to 118, and the root is 10.86 days.

Why a shared buffer

Padding every task hides the safety where it is easily wasted, because work expands to fill the time. Pooling the safety into one buffer at the end of the chain is shorter than the sum of the padding, because it is unlikely that every task will run long at once.

The cut and paste method is simple and conservative. The root method gives a smaller buffer when there are many tasks, because the safety of independent tasks adds up more slowly than a plain sum.

Using the buffer well

A buffer size is only the start. During the project, watch how much of the buffer has been used compared with how much of the chain is done, and act when the buffer is being used faster than the progress. Both methods are rules of thumb and the root method assumes task delays are independent.

Estimate one uncertain task with the Three Point Estimate Calculator, simulate the whole schedule with the Monte Carlo Project Duration Simulator, and reserve money for risks with the Contingency Reserve Simulator.

Assumptions and limits

  • All tasks are on one chain of work that follows one after another. Parallel paths and resource conflicts are not modeled.
  • Aggressive estimates must be 0 or more and no more than the safe estimates.
  • Up to 100 tasks are read. Numbers can have decimals.
  • The unit is a label only and does not change the arithmetic.
  • Nothing typed here leaves your browser.

Formulas reviewed October 10, 2026. See the calculation methodology for how SumPanda rounds, tests and sources its formulas.

Frequently asked questions

Which method should I use?

Cut and paste is the easiest to explain and gives a larger buffer. The root method is lighter for chains of many tasks. Use the one your team already knows, and compare the two in the stats.

What is a safe estimate?

The time you would quote to be nearly sure of finishing, often with a margin for problems. The aggressive estimate is the time that is achievable if there are few interruptions.

Why is the root buffer smaller?

Squaring and then taking the root of the sum grows more slowly than adding up and halving when there are many tasks. It assumes delays do not all happen together.

Can the buffer be negative?

No. Aggressive estimates cannot exceed safe ones, so the safety removed is zero or more and so is the buffer.